A1 - GENERAL SUPPLY TARIFF - RESIDENTIAL | GoP Applicable w.e.f Oct 2022 | |||||
Fixed Charges | Variable Charges | |||||
Rs/KW/Month | Rs/KWH | |||||
a) For sanctioned load upto 5 KW |
|
| ||||
| i) Upto 50 units - Life Line | - | 3.95 | |||
ii) 51-100 units - Life Line | - | 7.74 | ||||
iii) 1-100 units | - | 7.74 | ||||
iv) 101-200 units | - | 10.06 | ||||
| v) 1-100 units | - | 13.48 | |||
vi) 101-200 units | - | 18.95 | ||||
vii) 201-300 units | - | 22.14 | ||||
viii) 301-400 units | - | 25.53 | ||||
ix) 401-500 units | - | 27.74 | ||||
x) 501-600 units | - | 29.16 | ||||
xi) 601-700 units | - | 30.30 | ||||
xii) Above 700 units | - | 35.22 | ||||
b) For sanctioned load 5 KW & above |
|
| ||||
| Time of Use (TOU) Peak | - | 34.39 | |||
| Time of Use (TOU) Off-Peak | - | 28.07 | |||
A2 - GENERAL SUPPLY TARIFF - COMMERCIAL | GoP Applicable w.e.f Oct 2022 | |||||
Fixed Charges | Variable Charges | |||||
Rs/KW/Month | Rs/KWH | |||||
a) For sanctioned load less than 5 KW | - | 30.25 | ||||
b) For sanctioned load 5 KW & above | 500.00 | 31.93 | ||||
c) Time of use |
|
| ||||
| TOU Peak | 500.00 | 33.85 | |||
| TOU Off-Peak | 500.00 | 27.88 | |||
d) | Electric Vehicle Charging Station |
| 31.93 | |||
A3 - GENERAL SERVICES | GoP Applicable w.e.f Oct 2022 | |||||
Fixed Charges | Variable Charges | |||||
Rs/KW/Month | Rs/KWH | |||||
| General Services |
| 29.81 | |||
B - INDUSTRIAL SUPPLY TARIFF | GoP Applicable w.e.f Oct 2022 | |||||
Fixed Charges | Variable Charges | |||||
Rs/KW/Month | Rs/KWH | |||||
| B-1 Upto 25 KW (at 400/230 Volts) | - | 26.83 | |||
| B-2(a) 25-500KW (at 400 Volts) | 500.00 | 26.33 | |||
| Time of use |
|
| |||
| B-1(b) Upto 25KW Peak | - | 30.39 | |||
| B-1(b) Upto 25KW Off-Peak | - | 24.83 | |||
| Time of use |
|
| |||
| B-2(b) 25-500KW (at 400 Volts) Peak | 500.00 | 30.33 | |||
| B-2(b) 25-500KW (at 400 Volts) Off-Peak | 500.00 | 24.62 | |||
| For all Loads upto 5000 KW (at 11,33KV) |
|
| |||
| B-3 Peak | 460.00 | 30.33 | |||
| B-3 Off-Peak | 460.00 | 24.53 | |||
| For all Loads (at 66,132KV & above) |
|
| |||
| B-4 Peak | 460.00 | 30.33 | |||
| B-4 Off-Peak | 460.00 | 24.43 | |||
C - BULK SUPPLY TARIFF | GoP Applicable w.e.f Oct 2022 | |||||
Fixed Charges | Variable Charges | |||||
Rs/KW/Month | Rs/KWH | |||||
C-1 For supply at 400/230 Volts |
|
| ||||
| a) Sanctioned load upto 5 KW | - | 30.93 | |||
| b) Sanctioned load above 5 & Upto 500 KW | 500.00 | 30.43 | |||
C-2 (a) For supply at 11,33KV upto & including 5000KW | 460.00 | 30.23 | ||||
C-3 (a) For supply at 66KV & above & sanctioned load above 5000KW | 440.00 | 30.13 | ||||
| Time of Use (Optional) |
|
| |||
C-1 (c)For supply at 400/230 Volts above 20 KW & Upto 500KW |
|
| ||||
| Peak | 500.00 | 33.85 | |||
| Off-Peak | 500.00 | 27.25 | |||
C-2 (b) For supply at 11,33KV upto & including 5000KW |
|
| ||||
| Peak | 460.00 | 33.85 | |||
| Off-Peak | 460.00 | 27.05 | |||
C-3 (b) For supply at 66KV & above & sanctioned load above 5000KW |
|
| ||||
| Peak | 440.00 | 33.85 | |||
| Off-Peak | 440.00 | 26.95 | |||
D-AGRICULTURAL T/WELL TARIFF | GoP Applicable w.e.f Oct 2022 | |||||
Fixed Charges | Variable Charges | |||||
Rs/KW/Month | Rs/KWH | |||||
| D-1(a) SCARP Less than 5KW | - | 26.93 | |||
| D-2 Agricultural Tube-Wells | 200.00 | 16.60 | |||
| D-1(b) SCARP 5KW & above |
|
| |||
| TOU Peak | 200.00 | 29.88 | |||
| TOU Off-Peak | 200.00 | 22.60 | |||
| D-2(b) Agricultural 5KW & above |
|
| |||
| TOU Peak | 200.00 | 16.60 | |||
| TOU Off-Peak | 200.00 | 16.60 | |||
E - TEMPORARY SUPPLY TARIFF | GoP Applicable w.e.f Oct 2022 | |||||
Fixed Charges | Variable Charges | |||||
Rs/KW/Month | Rs/KWH | |||||
| E-1(i) Residential Supply | - | 34.53 | |||
| E-1(ii) Commercial Supply | - | 30.64 | |||
| E-2 Industrial Supply | - | 27.91 | |||
F - SEASONAL SUPPLY TARIFF | GoP Applicable w.e.f Oct 2022 | |||||
Fixed Charges | Variable Charges | |||||
Rs/KW/Month | Rs/KWH | |||||
| 125% of relevant industrial tariff |
| ||||
G - PUBLIC LIGHTING | GoP Applicable w.e.f Oct 2022 | |||||
Fixed Charges | Variable Charges | |||||
Rs/KW/Month | Rs/KWH | |||||
| Street Lighting | - | 29.93 | |||
H - RESIDENTIAL COLONIES OF INDUSTRIES | GoP Applicable w.e.f Oct 2022 | |||||
Fixed Charges | Variable Charges | |||||
Rs/KW/Month | Rs/KWH | |||||
| Residential Colonies attached to Industrial premises | - | 29.93 | |||
I - RAILWAY TRACTION | GoP Applicable w.e.f Oct 2022 | |||||
Fixed Charges | Variable Charges | |||||
Rs/KW/Month | Rs/KWH | |||||
| Railway Traction | - | 29.93 | |||
K - AJK | GoP Applicable w.e.f Oct 2022 | |||||
Fixed Charges | Variable Charges | |||||
Rs/KW/Month | Rs/KWH | |||||
1 | AJK | 440.00 | 27.15 | |||
| TOU Peak | 440.00 | 32.85 | |||
| TOU Off Peak | 440.00 | 25.95 | |||
2 | Rawat Lab. |
| 29.93 |